装甲装备月份维修计划优化制订方法研究 被引量:1

Research on Optimization Formulation Method of Armored Equipment Month Maintenance Plan
原文传递
导出
摘要 分析装甲装备月份维修计划的制订目前存在的问题,通过研究任务与装甲装备月份维修计划之间的相关关系,提出了根据任务的强度确定维修时机为优化目标的维修计划优化模型,统筹考虑维修资源、规章制度等因素。经LINGO软件仿真验证,结果显示该模型能够极大化装备的使用效益,实现科学化、精确化的送修,以及对装备的集约化管理。 The problems were analyzed that lay in the formulation of the armored equipment month maintenance plan. Based on researches about the relationship between the mission and the month maintenance plan, a maintenance plan optimization formulation model was brought forward. The model took factors such as maintenance resources, rules and regulations into overall consideration, and selected maintenance opportunity based on the strength of the mission as optimization goal. The model was validated by LINGO simulation. The result shows that the model can not only maximize the use efficiency, but also realize the scientific and precise delivery and the intensive management of the equipment which needs preventive maintenance.
出处 《系统仿真学报》 CAS CSCD 北大核心 2010年第11期2683-2685,共3页 Journal of System Simulation
关键词 装甲装备 月份维修计划 优化制订方法 仿真 armored equipment month maintenance plan optimization formulation model simulation
  • 相关文献

参考文献6

  • 1王铁宁.装各保障信息系统工程[M].北京:装甲兵工程学院,2003:323-325.
  • 2楼明政 姚富山.科学制定旅(团)级装甲装备使用、维修计划.装甲兵技术学院学报,2007,(3):39-40.
  • 3张涛,郭波,谭跃进.面向任务的维修资源配置决策支持系统研究[J].兵工学报,2005,26(5):716-720. 被引量:15
  • 4王云涛,沈洪,王建平.使修计划中的等量关系与约束条件[C]//应用高新技术提高维修保障能力会议论文集,北京:马世宁,甘茂治,2005:768-771.
  • 5李耀华,谭娜,郝贵和.飞机维修计划优化模型与算法研究[J].控制工程,2008,15(1):99-102. 被引量:13
  • 6谢金星,薛毅.优化建模与LINGO软件[M].北京:清华大学出版社.2007:16-17.

二级参考文献16

  • 1刘春林,何建敏,盛昭瀚.应急系统多出救点选择问题的模糊规划方法[J].管理工程学报,1999,13(4):21-24. 被引量:12
  • 2陶冶,白存儒,由嘉.基于遗传算法的起降航班动态排序模型的研究[J].中国民航学院学报,2005,23(4):6-9. 被引量:8
  • 3Bottcher J, Drexl A, Kolisch R. A branch and bound procedure for project scheduling with partially renewable resource constraints[C]. Proceedings of the 5th International Workshop on Project Management and Scheduling, Poznan, 1996, 4:48 - 51.
  • 4Brucker P, Drexl A, Mohring R, et al. Resource-constrained project scheduling: Notation, classification, models and methods[J]. European Journal of Operational Research, 1999, 112:3 -41.
  • 5Herroelen W, Reyck B D, Demeulemeester E. Resource-constrained project scheduling: a survey of recent developments[J].Computers & Ops. Res,1998, 25(4) :279 - 302.
  • 6Kaplan L. Resource-constrained project scheduling with preemption of jobs[D]. Ann Arbor, MI:University of Michigan, 1988.
  • 7Jansen J, Ohring S. Approximation algorithms for time constrained scheduling[J]. Information and Computation, 1997,132: 85- 108.
  • 8Wybo Jean-Luc. FMIS: a decision support system for forest fire prevention and fighting[J]. IEEE Transactions on Engineering Management, 1998, 45(2) : 127 - 131.
  • 9Hays W W. Reduction of earthquake risk in the United States:bridging the gap between research and practice[J]. IEEE Transactions on Engineering Management, 1998, 45(2) : 176 - 180.
  • 10Moudani El W, Mora-Camino F. A dynamic approach for aircraft assignment and maintenance scheduling by airlines[J] .Journal of Air Transport Management, 2000,6(4) : 233-237.

共引文献27

同被引文献10

引证文献1

二级引证文献3

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部