矿井高压电网漏电保护装置动作参数分析 被引量:10

An analysis of the tripping parameters of earth-leakage protection devices for high-voltage electric network in mines
在线阅读 下载PDF
导出
摘要 对于中性点不接地的矿井高压电网,漏电保护装置的零序电压动作值是其重要技术数据之一.当其整定值确定之后,漏电保护装置的漏电动作电阻值(R)及其相关的电网每相对地电容值(C),即可由本文所给的简化计算公式求得.该公式是在忽略绝缘电阻(r)的条件下求得的.在实际电网中使用,计算误差不大.该方法便于现场根据实测的绝缘参数变化范围进行调节. For an ungroundedneutral highvoltage electric network in mines, the tripping value of zerosequence voltage of the earthleakage protection devices is one of its important technical data. When it is set up, the tripping leakage resistance (R) and corresponding capacitance of the network to the ground per phase (C) can be calculated by the simplified formula presented in this paper in the condition of neglecting the insulance to the ground (r). Owing to the fact that the error of calculation for the real network is not very big, this method can be easily used in practice, especially for a range of measured insulation parameters of the power system.
出处 《煤炭学报》 EI CAS CSCD 北大核心 2003年第2期205-209,共5页 Journal of China Coal Society
基金 国家自然科学基金资助项目(50077022)
关键词 矿井 高压电网 漏电保护装置 中性点不接地 零序电压 power system in mines earth-leakage protection tripping values of parameters
  • 相关文献

参考文献1

二级参考文献2

  • 1顾永辉 冯继武 等.煤矿安全手册[M].北京:煤炭工业出版社,1992.226-235.
  • 2胡天禄 郁继裳 等.煤矿电工手册(修订本,第2分册·矿井供电(下))[M].北京:煤炭工业出版社,1998.988-1002.

共引文献4

同被引文献58

引证文献10

二级引证文献23

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部