摘要
地下工程施工过程是一个复杂的多因素影响的系统工程 ,通过对施工进度计划的PERT网络模型进行计算机仿真 ,得出了工期的概率分布和均值、各工序处于关键线路上的概率以及可引起关键线路转移的主要工序等 ,可以科学合理地安排施工 。
The design of construction management in underground engineering is a complicated multifactor system. In this paper, how to simulate a PERT network model of construction schedule with computer is described in order to get the probability distribution of project time limit, working procedure on critical path etc, which can be used to arrange a project with the shortest time and resources.
出处
《地下空间》
CSCD
2003年第1期9-11,共3页
Underground Space