流水作业法在目前的施工组织设计中应用比较广 ,但在实际应用中常常遇到如何确定施工段合理次序的问题。实践证明 ,约翰逊———贝尔曼法则能够较好地解决这个问题。本文主要介绍约翰逊———贝尔曼法则及其在流水作业中的应用 。
Production line is widely applied in construction organization design,but in practice ,how to determine the section order is a problem.It is proved that Johnson-Belman law can solve the problem.The law and its application in line production are mainly introduced so that construction organization design can be conducted properly.
出处
《河南城建高等专科学校学报》
2001年第3期62-63,共2页
Journal of Henan Urban Construction Junior College