国产化400 MW抽水蓄能机组背靠背启动的试验分析 被引量:3

Experimental Analysis of the Back-to-back Start-up in a Domestic Design 400 MW Pumped Storage Unit
在线阅读 下载PDF
导出
摘要 随着智能电网的发展,抽水蓄能电站也进入了建设投产的快速增长期。背靠背启动是多数抽水蓄能机组水泵方向启动的备用启动方式。首先简要分析了背靠背启动的原理,针对国内某400 MW机组,介绍了背靠背启动的监控流程。然后,通过现场试验的方式,分析试验结果,给出了拖动机导叶开启规律和拖动机与被拖动机励磁电流选择的建议。最后,分析了现场试验过程中,几次背靠背启动失败案例的原因,给出了现场解决的方法。 With the development of smart grid, plenty of the pumped storage units are constructing. The back-to-back start-up is used as the standby way in pumping mode. In this paper, the principle of the back-to-back start-up is briefly analyzed. The monitor process of back-to- back startup is introduced for a domestic 400 MW pumped storage unit. The guide vane opening principle and the field currents in both machines are chosen and proposed on the basis of experimental results. The reasons and solutions of two failure start-up cases are also presented.
出处 《中国农村水利水电》 北大核心 2017年第9期186-190,共5页 China Rural Water and Hydropower
关键词 抽水蓄能 背靠背启动 导叶开启规律 pumped storage unit back-to-back start-up guide vane opening principle
  • 相关文献

参考文献5

二级参考文献18

共引文献27

同被引文献27

引证文献3

二级引证文献17

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部