摘要
建立了具有提前/拖期惩罚的热轧钢管批调度问题的混合整数非线性规划模型,提出并证明了给定合同排序下的最优组批方式,从而将原问题转化为易求解的合同排序问题.同时,建立了转化问题的数学模型并设计了遗传算法.仿真实验验证了模型和算法的有效性.
The hot rolling steel tube batch scheduling problem with earliness/tardiness penalties as a mixed integer non-linear programming model is discussed. The optimal batching method under given order sequencing is presented and proved. Based on the optimal batching method, the original problem is changed into an easier sequencing problem. A model for the new problem is then developed and a genetic algorithm is designed. The computation results show the effectiveness of the model and algorithm.