订货生产式企业作业任务交货期决策研究 被引量:8

Due-Date Assignments for Make-to-Order Enterprises
在线阅读 下载PDF
导出
摘要 分析了工序时间的随机性特征及其对任务完工期的影响及作业任务交货期决策的重要性,确定任务交货期的方式,指出在工序时间随机性特征条件下,任务交货期应为一个区间,建立了以损失费用最小化为目标的最优交货期时区模型、最优最早交货期模型、最优完工时间偏差控制模型,采用计算机迭代法验证了上述各模型的有效性。 This paper analyzes the stochastic features of operation,and its effects on completed time of job.Also the paper discusses the importance of due-date assignment and methods to predict completed time of job.On condition of stochastic features of operation,the due-date is a period of time.For the purpose of minimizing the cost of job,the paper develops some optimization decision-making models,such as the model of due-date of job,earliest due-date of job and standard variance of processing time control.The validity of those models is proved by computer iterative method.
出处 《工业工程》 2004年第1期26-28,共3页 Industrial Engineering Journal
基金 广东省自然科学基金资助项目(20010047) 广东省教育厅人文社科基金资助项目(01SJD630001)
关键词 计算机迭代法 作业任务交货期 随机性特征 订货生产式企业 stochastic operation due-date decision processing time
  • 相关文献

参考文献6

  • 1Chang Feng-chang R. A study of factors affecting due-date predictability in a simulated dynamic job shop[J]. Journal of Management Science, 1998,13(6) : 393-399.
  • 2Griffin Thmas E. On departure from estimated processing times[D]. PH.D Dissertation. School of Business And Entrepreneurship NOVA Southeastern University. 1998. 79-85.
  • 3Duenyas, Hopp W J. Quoting customer lead times [ J ]. Journal of Management Science, 1995,41 ( 1 ) : 43-57
  • 4KR Baker. Sequencing rules and due-date assignments in a jobshop[J]. Management Science, 1984,30(9) : 1093-1104.
  • 5张毕西,刘永清.随机型作业计划动态排序方法研究[J].华南理工大学学报(自然科学版),2000,28(1):122-129. 被引量:8
  • 6张毕西,刘永清.静态非流水型作业排序方法研究[J].华南理工大学学报(自然科学版),1998,26(12):65-70. 被引量:5

二级参考文献8

共引文献9

同被引文献58

引证文献8

二级引证文献20

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部