巫山长江公路大桥是一座主净跨为 4 6 0 m的中承式钢管混凝土拱桥 ,主拱肋采用斜拉扣挂法无支架缆索吊装施工 ,已于 2 0 0 3年 4月中旬成功合拢。该桥是对我国无支架缆索吊装系统的进一步完善。其吊装施工中的一些关键技术 ,在得到进一步突破的同时 。
Wushan Yangtze River Highway Bridge is a half-through concrete-filled steel pipe arch bridge with a main clearance span of 460 m. The erection of main arch ribs adopt cable-stayed buckled method of non-support cable hoisting system, which were closed successfully in this April. The example perfects further for the non-support cable hoisting system in our country. Among them, the key techniques in hoisting construction are further broken through, it may be used for technique reference for arch bridge construction.
出处
《公路》
北大核心
2003年第11期7-11,共5页
Highway
关键词
公路桥
中承式钢管混凝土拱桥
钢管拱肋
吊装施工
施工技术
无支架缆索吊装
Wushan Yangtze River Highway Bridge
concrete-filled steel pipe arch bridge
non-support cable hoist
construction technique