摘要
为有效解决资源约束条件下的船舶舾装项目进度管理问题,提出一种基于全局项目资源调度的船舶舾装项目进度管理方法。采用层次分析法确定项目中各子任务对某类关键资源的分配优先级,构建资源约束条件下的项目资源调度框架。采用网络计划技术和基于优先权规则的启发式算法,分别对核心任务和非核心任务进行资源调度与配置。研究结果表明,通过采用该船舶舾装项目进度管理方法,能提前干预舾装项目的资源配置,有效提升资源利用率,解决资源紧张和资源浪费等问题。
To address schedule management challenges in resource-constrained ship outfitting projects,a progress management model is developed based on global project resource scheduling.This model utilizes the AHP(Analytic Hierarchy Process)to decide resource allocation priorities for subtasks,establishing a resource scheduling framework under constrained conditions.Network planning techniques and priority rule-based heuristic algorithms are applied to separately allocate resources for critical and non-critical tasks.Trial results demonstrate that this model enables proactive resource configuration interventions,effectively improves resource utilization efficiency,and resolves issues of resource shortages or wastage.
作者
何强
李宽
邰能灵
周靖淞
HE Qiang;LI Kuan;TAI Nengling;ZHOU Jingsong(Warship Automatic System Division,Shanghai Ship and Shipping Research Institute Co.,Ltd.,Shanghai 200135,China;School of Electronic Information and Electrical Engineering,Shanghai Jiao Tong University,Shanghai 201100,China;Shipbuilding Division 1,CSSC Huangpu Wenchong Shipbuilding Co.,Ltd.,Guangzhou 510000,China)
出处
《上海船舶运输科学研究所学报》
2025年第2期18-27,共10页
Journal of Shanghai Ship and Shipping Research Institute
关键词
船舶舾装项目
资源配置
层次分析法
资源约束
进度管理
ship outfitting project
resource allocation
AHP(Analytic Hierarchy Process)
resource constraint
schedule management