综合管廊电力支架预埋螺栓固定方式的改进做法 被引量:2

IMPROVEMENT METHOD FOR PRE-EMBEDDED BOLT FIXING OF COMPREHENSIVE PIPE GALLERY POWER BRACKET
在线阅读 下载PDF
导出
摘要 北京通州文化旅游区萧太后河南街综合管廊体量大、线性长,弧形部位多,纵向坡度较大,其中电力舱墙体预埋螺栓20 220个,致使模板开孔量大。在不改变既定模板施工方法的基础上,采用预埋螺栓开孔后的固定方式,可简化工序,提高工作效率,降低人工及材料费用,保证螺栓的预埋质量。 The comprehensive pipe gallery project on Xiaotaihou river south street in Beijing Tongzhou Culture and Tourism Zone has big volume,long distance,many arch positions,big longitudinal slope and large workload of formwork openings,including 20220 pre-embedded bolts on the power cabin wall.Without changing the existing formwork construction method,the fixing method after pre-embedded bolt opening was adopted to simplify the construction sequence,improve the construction efficiency,reduce the labor and material cost and guarantee the bolt pre-embedding quality.
作者 王伟 WANG Wei(BCEG Civil Engineering Co.,Ltd.,100015,Beijing,China)
出处 《建筑技术》 2020年第7期857-858,共2页 Architecture Technology
关键词 综合管廊 预埋螺栓 螺栓固定 comprehensive pipe gallery pre-embedded bolt bolt fixing
  • 相关文献

参考文献2

二级参考文献6

共引文献1

同被引文献21

引证文献2

二级引证文献3

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部