摘要
团柏煤矿生产时期陷落柱发育,在全区域带压的下组煤不到6 km2的采掘范围内,揭露陷落柱达107个,其中,导含水的有46个,因此在水源的判别、陷落柱的精准圈定以及综合治理方面取得了丰富的经验。以10-215工作面陷落柱的初步圈定、精准探查以及注浆加固杜绝水害发生为主要阐述内容,介绍推广相关防治水技术经验。
During the production period of Tuanbai Coal Mine,collapse pillars developed.Within the mining area of less than 6 km2 of lower group coal with pressure in the whole area,107 collapse pillars were exposed,of which 46 were water diversion ones.Therefore,rich experience had been gained in water source identification,precise delineation of collapse pillars and com-prehensive treatment.Based on the preliminary delineation,precise exploration and grouting reinforcement of collapse pillars in 10-215 working face,this paper mainly expounded the experience of popularizing relevant water control technology.
作者
夏志阳
XIA Zhiyang(Water Control Engineering Technology Branch Company of Yunxia Company,Huozhou Coal Electricity Group of Shanxi,Huozhou 031400,Shanxi,China)
出处
《能源与节能》
2020年第4期142-144,共3页
Energy and Energy Conservation
关键词
带压开采
陷落柱
注浆加固
异常区
mining under pressure
collapse pillars
grouting reinforcement
abnormal area