基于BIM技术水闸项目进度优化研究 被引量:2

Research on Sluice Project Schedule Optimization Based on BIM Technology
在线阅读 下载PDF
导出
摘要 工程建设行业正在蓬勃发展,工程项目管理面临巨大挑战,传统进度控制方法无法满足现代化管理的需要。本文运用Revit建立三维模型,P6编制进度计划,将三维模型与进度计划载入Navisworks软件,进行施工进度动态模拟,利用BIM技术的模拟性、协同性及可视化的优势,提前发现问题,进行进度计划的调整,并进行实际进度开展情况的监测、调整。随着信息技术推进,BIM技术作为一种新兴的信息技术,应用到现代的工程项目建设中,为工程管理模式提供新的解决方案。 With the rapid development of engineering construction industry,engineering project management is facing great challenges.The traditional progress control method can not meet the needs of modern management.In this paper,Revit is used to build a three-dimensional model,P6 is used to prepare the schedule,and the three-dimensional model and schedule are loaded into NavisWorks software to carry out dynamic simulation of construction schedule.Using the advantages of BIM Technology such as simulation,coordination and visualization,we can find problems in advance,adjust the schedule,monitor and adjust the actual progress.With the advancement of information technology,BIM Technology,as a new information technology,is applied to the construction of modern engineering projects to provide new solutions for the project management mode.
作者 王婷婷 孙少楠 胡威锋 聂运凯 WANG Ting-ting;SUN Shao-nan;HU Wei-feng;NIE Yun-kai(North China University of Water Resources and Electric Power,Zhengzhou 450046,China)
出处 《价值工程》 2020年第2期217-219,共3页 Value Engineering
基金 华北水利水电大学大学生创新创业训练计划项目(2018XB190)
关键词 水闸 BIM 进度管理 进度优化 可视化模拟 sluice BIM schedule management schedule optimization visual simulation
  • 相关文献

参考文献4

二级参考文献15

  • 1张建平,曹铭,张洋.基于IFC标准和工程信息模型的建筑施工4D管理系统[J].工程力学,2005,22(S1):220-227. 被引量:111
  • 2于金勇,林敏.BIM技术在地铁安装工程中的应用[J].土木建筑工程信息技术,2013,5(2):86-91. 被引量:22
  • 3Huang T, Kong C W, Guo H L, Baldwin A, Li H. A virtual prototyping system for simulating construction processes [J]. Automation in Construction, 2007, 16( 5 ): 576-585.
  • 4Li H, Huang T, Kong C W, Guo H L, Baldwin A, Chan N, Wong J. Integrating design and construction through virttial prototyping[J]. Automation in Construction, 2008, 17 ( 8): 915-922.
  • 5Li H, GUO H L, Skibniewski M J, Skitmore M. Using the IKEA model and Virtual Prototyping technology to improve construction process management[J]. Construction Management and Economics, 2008, 26 ( 9 ): 991-1000.
  • 6Li H, Guo H L, Skitmore M, Huang T, Chan N, Chan G. Rethinking prefabricated construction management using the VP-based IKEA model in Hong Kong[J]. Construction Management and Economics, 2011, 29 ( 3 ): 233-245.
  • 7Guo H L, Li H, Skitmore M. Life cycle management of construction projects based on Virtual Prototyping technology[J]. Journal of Management in Engineering, ASCE, 2010, 26 (1): 41 47.
  • 8Guo H L, Li H, Chan G, Skitmore M. Using game technologies to improve the safety of construction plant operations[J]. Accident Analysis and Prevention, 2012, 48: 204-213.
  • 9胡振中.基于BIM和4D技术的建筑施工冲突与安全分析管理[D].北京:清华大学,2009.
  • 10李恒,郭红领,黄霆,陈镜源,陈景进.BIM在建设项目中应用模式研究[J].工程管理学报,2010,24(5):525-529. 被引量:160

共引文献198

同被引文献16

引证文献2

二级引证文献13

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部