双线隧道暗挖施工技术及其数值模拟分析 被引量:27

Dark-excavation Construction Techniques of the Double-line Tunnel and Its Numerical Simulation Analysis
在线阅读 下载PDF
导出
摘要 某市轨道交通三号线某区间双线隧道 ,隧道断面大 ,埋深浅 ,岩性差 ,且隧道顶部离3 0号、3 1号楼桩基很近。针对上述特点 ,提出用CRD工法加辅助工法施工 ,并采用弹塑性有限单元法对该工法按施工步骤进行分步模拟计算 ,为施工设计提供依据。 For the double line tunnel of a section in the rail transit No.3 of certain city, there is a large cross section, a shallow overburden and poor quality of the rock, besides, the top of the tunnel is close to the pile foundation of No.30 and No.31 buildings. Based on abovementioned characteristics, the CRD process and auxiliary process are proposed, and an elastic-plastic finite element method is used to simulate calculation for the process according to its construction steps. It can serve as a basis for the design of construction.
出处 《地下空间》 CSCD 2002年第4期285-289,305,共6页 Underground Space
关键词 地铁 双线隧道 CRD工法 数值计算 metro double line tunnel CRD process auxiliary process numerical calculation
  • 相关文献

参考文献4

二级参考文献10

  • 1周维恒.高等岩石力学[M].北京:水利电力出版社,1990..
  • 2[9]丁春林,刘建国,宫全美. 广州市地铁二号线盾构隧道衬砌内力计算及地层变形分析[R].上海:同济大学沪西校区岩土工程研究所,2000
  • 3丁春林,柴家坡隧道有限元分析报告,1996年
  • 4潘昌实,隧道力学数值方法,1995年,63页
  • 5尚岳全,工程地质研究中的数值分析方法,1991年,96页
  • 6团体著者,铁路隧道设计规范(TBJ3-85),1987年
  • 7陶振宇,岩石力学的理论与实践,1981年,362页
  • 8肖树芳,岩体力学,1967年,119页
  • 9尹旅超 朱振宏 李玉珍编译.日本隧道盾构新技术[M].武汉:华中理工大学出版社,1996..
  • 10丁春林,周顺华.注浆加固对复线隧道滑动面和周边围岩稳定性的影响[J].上海铁道大学学报,1998,19(12):6-11. 被引量:1

共引文献46

同被引文献88

引证文献27

二级引证文献186

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部