网络规划法在梯级水电站短期优化调度中的应用 被引量:1

THE APPLICATION OF NETWORK PROGRAMMING METHOD ON THE SHORT TERM OPTIMAL SCHEDULING FOR CASCADED HYDROPOWER STATIONS
在线阅读 下载PDF
导出
摘要 用网络规划法对梯级水电站日负荷最优分配问题进行了探讨,提出了一种新的网络模型,在开机组合业已给定的条件下,直接将负荷分配到机组。还对算法进行了讨论,并在微机上对一个实际的梯级水电站进行了试算。计算结果表明该模型和算法是正确的、适用的。 The problem of the short term economic scheduling for cascaded hydropower stations is discussed with the network programming method. A new network model is built to dispatch the load to each unit when the unit commitment is determined. An algorithm of the minimal cost maximal flow is also discussed using the model and the algorithm to the Longxi River Cascaded Hydropower Stations, the computational result on the microcomputer VAX II shows that the model and the algorithm are correct and applicable.
出处 《重庆大学学报(自然科学版)》 EI CAS CSCD 1991年第1期25-32,共8页 Journal of Chongqing University
关键词 水电站 梯级 调度 网络规划法 network programming method cascaded hydropower stations short term optimal scheduling load optimal dispatch minimal cost maximal flow
  • 相关文献

参考文献7

  • 1刘广一,中国电机工程学报,1988年,8卷,6期,9页
  • 2夏祖治,中国电机工程学报,1988年,8卷,3期
  • 3Song Yianmin,1988年
  • 4孙东川,网络流规划,1988年
  • 5段虞荣,1987年
  • 6夏清,清华大学学报,1987年,27卷,4期,1页
  • 7夏清,中国电机工程学报,1985年,5卷,4期,48页