摘要
某CPR1000机组自调试运行以来,汽轮发电机组并网初始负荷与设计值有偏差较大的情况,使反应堆发生了堆芯过冷的情况,影响机组的安全运行。本文通过对并网初始负荷偏差的原因进行分析,并给出了对应的解决方案。
Since the commissioning and operation of CPR1000 unit, there has been big deviation between the steam turbine generator unit grid connection initial load and the designed value, which causes overcooling of the reactor core and affects the safe operation of the unit. This article analyzes the causes of deviation of the grid connection initial load and proposes corresponding solution.
出处
《价值工程》
2015年第13期49-50,共2页
Value Engineering
关键词
汽轮机
并网
初始负荷
steam turbine
grid connection
initial load