韶钢1号高炉长时间无计划休风的炉况恢复实践 被引量:3

Practice of Blast Recovery of Long Time Unplanned Stoppage for No.1 BF at SISG
在线阅读 下载PDF
导出
摘要 韶钢1号高炉2014年2月11日因炉顶上料系统主卷扬高速轴断裂,被迫无计划休风达15 h.通过制定合理的复风方案,确定各项操作制度,加强渣铁排放,精细化的调节和操作控制,11日15:20恢复送风,23:00炉内风压、风量等操作参数快速恢复到正常水平,避免了因此造成炉凉或炉缸冻结等工艺事故. No. 1 blast furnace was forced to unplanned downtime for up to 15 hours for top charging high speed shaft hoist system in fault on February 11,2014. The blast furnace recovered ventilation at 15:20 by making up the reasonable reblow solution, determining the operating system, strengthening the iron slag discharge, fine adjustment and control, and then furnace air pressure and other operating parameters quickly returned to normal level at 23:00, which avoided the process accidents such as the hearth cooling,the hearth chill.
出处 《南方金属》 CAS 2014年第6期55-58,共4页 Southern Metals
关键词 设备事故 无计划休风 复风方案 炉况恢复 equipment accident unplanned downtime reblow scheme recovery
  • 相关文献

参考文献2

  • 1张殿有.高炉冶炼操作技术[M].北京:冶金工业出版社.2007:158.
  • 2周传典主编.高炉炼铁生产技术手册[M].北京:冶金工业出版社,2008:32.

共引文献56

同被引文献9

引证文献3

二级引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部