摘要
TCA2 0 0 3全站仪是近几年问世的测量机器人。利用它对大型工程建 (构 )筑物进行外部变形观测 ,具有精度高、工效高、所获取的数据准确可靠等优点。在二滩水电站外部变形监测中 ,采用同精度仪器与 TCA2 0 0 3全站仪 ,在相同条件下施测平面控制基准网和监测网 ,以实测的数据进行对比 ,验证了 TCA2 0 0 3全站仪用于变形监测的优越性 。
The TCA2003 total station is a surveying robot which has been developed recently. It has the advantages of high precision and high work efficiency in deformation observation for large buildings and structures. In the surface deformation observation of Ertan Hydropower Station, the TCA2003 total station and some equipment of the same precision are used in the horizontal control survey datum network and monitoring network under the same condition. The measured data prove the superiorities of the TCA2003 total station in deformation observation. Some points which should be noticed in using the TCA2003 total station are pointed out.
出处
《水电自动化与大坝监测》
2002年第2期34-38,共5页
HYDROPOWER AUTOMATION AND DAM MONITORING