通过MIKE21 BW模块计算苍南县石砰渔港建成后港内水域的波高变化。在分析港内水域波高增加的原因后,提出了3种消浪工程方案,通过数学模型计算论证了不同工程方案对渔港港域的消浪效果。
This paper uses the MIKE 21 BW module to calculate and research the height changes of waves after the completion of Shi Peng Secondary Fishing Port of Cangnan County.After analyzing the reasons of wave increment in the terminal operation area,this paper puts forward three engineering solutions before the vertical wall of the revetment and make an argument of the wave dissipation effect of every solution.