通过对新机组启动过程的全面振动监测 ,找到了机组振动的原因 ,提出了合理的解决办法 ,最终使机组振动达到优良水平。
Presents the identification of the causes for the vibration of power generating set No.2 by monitoring the whole start up process of this new power generating set and the actions taken to keep the vibration within the limits.
出处
《黑龙江电力》
CAS
2000年第6期32-33,共2页
Heilongjiang Electric Power
关键词
汽轮发电机组
振动
轴承
发电厂
dynamic rigidity
impact friction
dynamic balance
vibration of shaft
vibration of bushing