钢管混凝土柱与伸臂桁架连接节点试验研究 被引量:8

EXPERIMENTAL STUDY ON CONCRETE FILLED STEEL TUBE COLUMN TO OUTRIGGER TRUSS CONNECTION
原文传递
导出
摘要 该文以实际工程为背景,对超高层建筑中常采用的钢管混凝土柱与伸臂桁架连接节点进行了大比例模型滞回加载试验。试验结果表明试件具有较高的极限承载力,耗能能力较好,试件的破坏模式最终表现为桁架近加载梁的上弦杆变截面处翼缘受拉断裂以及荷载反向后的弦杆压曲变形,建议将变截面焊接连接位置向弦杆中部偏移并严格控制其焊缝质量。 Based on a practical engineering project, the large scale cyclic test on the connection between a concrete filled steel tube column and a outrigger truss is conducted. Test results indicate that specimens show relatively satisfying load carrying capacity as well as considerable ductility, and that the failure mode exhibit as the flange fracture of the upper chord and buckling under compression. It is suggested that the welding connection section should be moved to the middle of the upper chord and the welding quality should be control strictly.
出处 《工程力学》 EI CSCD 北大核心 2013年第B06期78-82,共5页 Engineering Mechanics
基金 国家自然科学基金重点项目(51038008)
关键词 钢管混凝土 伸臂桁架 极限承载力 试验研究 破坏模式 concrete filled steel tube outrigger truss ultimate capacity experimental research failure mode
  • 相关文献

参考文献9

  • 1费新华.伸臂桁架在超高层建筑中的应用[J].施工技术,2006,35(增刊):238-241.
  • 2Rutenberg A,Tal D.Lateral load response of belted tallbuilding structures[J].Engineering Structures,1987,9(1):53-67.
  • 3Smith B S,Salim I.Parameter study of outrigger-bracedtall building structures[J].Journal of the StructuralDivision,1981,107(10):2001-2014.
  • 4邓志恒,胡强,潘志明,徐冬晓.钢桁架连梁耗能性能试验研究及损伤分析[J].自然灾害学报,2009,18(6):38-43. 被引量:7
  • 5王斌,秦浩,赵宪忠,陈以一.“上海中心”钢-混凝土连接节点的试验研究[J].哈尔滨工业大学学报,2012,44(增刊):157-160.
  • 6Choi Chang-Koon.Advances in structural engineeringand mechanics[C]//Wang Bin,Qin Hao,ZhaoXianzhong,et al.Experimental research on key joints ofShanghai Tower.Seoul:Techno-Press,2011:298.
  • 7姚振纲,刘祖华.建筑结构试验[M].上海:同济大学出版社,1996:17-19.Yao Zhengang,Liu Zuhua.Architectural structureexperiment[M].Shanghai:Tongji University Press,1996:17-19.(in Chinese).
  • 8马臣杰,张良平,曹伟良,项兵,尚文红,顾建,沈捷攀.深圳京基金融中心巨型节点设计研究[J].建筑结构,2011,41(S1):1083-1087. 被引量:3
  • 9沈祖炎,等.钢结构基本原理[M],北京:中国建筑工业出版社,2005.

二级参考文献10

  • 1马臣杰,张良平,范重.优化技术在深圳京基金融中心中的应用[J].建筑结构,2009,39(S1):195-197. 被引量:22
  • 2姚谦峰,田洁,黄炜.密肋复合墙板耗能性能及地震损伤分析[J].世界地震工程,2006,22(4):5-12. 被引量:6
  • 3Powcll G H,Allahabadi R. Seismic damage prediction by deterministic methods:concepts and procedures[J].Earthquake Eng. Struct. Dyn. 1988,16(5) :719-734.
  • 4Fajfar P., Equivalent ductility factors taking into account low cycle fatigue [ J ]. Earthquake Eng. Struct. Dyn, 1992,21(10) :837-848.
  • 5Ghobarah A,Abon -Elfath H H,Biddah A. Response-based damage assessment of structures[J]. Earthquake Eng. Street. Dy. ,1999,28(1) :79-104.
  • 6Chai Y H, Romstad K M, Bird S M. Energy--based linear damage model for hish--intensity seismic loading [ J ]. Journal of Structural Enginering. 1995,121 (5) :857-864.
  • 7Gulkin P, Sozen M A. Inelastic responses of reinforced concrete structures to earthquake motions [ J ]. Journal of the American Concrete inst, 1974, 71 ( 12):604-610.
  • 8潘志明.新型组合连梁控制结构抗震性能研究[D].南宁:广西大学,2007.
  • 9马臣杰,张良平,范重.某超高层结构连接节点的非线性有限元分析[J].建筑结构,2009,39(9):60-62. 被引量:5
  • 10邓志恒,潘峰,陶晓光,唐光暹.新型组合连梁控制结构体系[J].世界地震工程,2003,19(3):6-11. 被引量:21

共引文献48

同被引文献71

引证文献8

二级引证文献36

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部