同步物流系统下准时化生产与配送调度问题研究 被引量:11

Research on production and distribution scheduling in assembly system with synchronous logistics
原文传递
导出
摘要 对于"加工-装配"行业而言,物流管理水平的高低直接决定了供应链绩效的好坏。本文以Supply Hub运作模式为背景,研究同步物流下装配系统中各节点的生产与配送调度问题。建立供应链各参与方的生产与配送模型,并通过规划求解得到供应商和制造商的最优生产周期、零部件的最优配送间隔以及零售商的最佳采购周期。最后,结合数值实验,对同步物流模式和传统物流模式下的供应链绩效进行了对比分析。研究结果表明:较之传统物流模式,基于同步化物流方式的装配系统总成本更低,这主要得益于库存成本的下降;由于采取拉动式的生产模式,因此同步物流系统下供应链中的生产和配送活动更加频繁;生产调整成本的增加提高了制造商的平均总成本,由此可见在同步物流系统下,供应商、制造商和零售商之间更需要相互协商和收益共享,从而实现多赢。 As for assembly industry, performance of supply chain is directly decided by the level of logistics management. Bosed on the setting of Supply Hub,the production and distribution issues of every node in an assembly system are studied. Therefore, the production-distribution system is mathematically modeled and solved by programming software. By doing so, the optimal production interval of suppliers and manu- facturer, and distribution frequency of parts, as well as the purchase cycle of retailer are got. The compar- ative analysis between traditional logistics mode and synchronous logistics mode is also taken. It is conclu- ded that: the assembly system based on synchronous logistics can generate lower total average cost because of inventory cost reduction. In the supply chain with synchronous logistics, suppliers and manufacturer produce and distribute more frequently. Although the total cost is reduced, more setup cost results in the increase of cost for manufacturer, which indicates participants should do well in cooperation and negotia- tion in order to make win-win .
出处 《中国管理科学》 CSSCI 北大核心 2012年第6期125-132,共8页 Chinese Journal of Management Science
基金 国家自然科学基金资助项目(71072035)
关键词 同步化物流 Supply HUB 装配系统 准时化生产与配送 synchronous logistics supply hub assembly system JIT manufacturing and distribution
  • 相关文献

参考文献14

  • 1Hahm J, Yano C A. The economic lot and delivery scheduling problem: the single itemcase [J]. Interna- tional Journal of Production Economics, 1992, 28 (2): 235-252.
  • 2Kim S L, Ha D. A JIT lot-splitting model for supply chain management: enhancing buyer-supplierlinkage [J]. International Journal of Production Economics, 2003, 86(1):1-10.
  • 3Khouja M. Synchronization in supply chains: implica tions for design andmanagement [J]. Journal of the op- erational Research Society, 2003, 54 (9) : 984- 994.
  • 4Kreng B, Wang I C. Economical delivery strategies of products in a JIT system under a global supply chain [J]. Int J Adv Manuf Technol, 2005,26:1421-1428.
  • 5Pundoor G, Chen Z hilong. Joint cyclic production and delivery scheduling in a two stage supply chain[J]. In- ternational Journal of Production Economics, 2009,119 (1) :55-74.
  • 6Low C, Li R K, Chang C M. Integrated scheduling of production and delivery with time windows[J]. Interna tional Journal of Production Research, forthcoming.
  • 7Lee W. A joint economic lot size model for raw material ordering, manufacturing setup, and finished goodsdeliv- ering [J]. Omega, 2005, 33(2): 163-174.
  • 8Cao Wujun, Hu Yujin, Li Chenggang, et al. Single set- up multiple delivery model of JIT system[J]. Int J Adv Manuf Technol, 2007, 33: 1222-1228.
  • 9Pundoor G. Integrated production-distribution schedu- ling in supplychains [D]. Maryland: University of Mar- yland, 2005.
  • 10Sana S S. A production-inventory model of imperfect quality products in a three-layer supply chain[J]. Deci- sion Support Systems, 2011, 50(2) :539-547.

二级参考文献35

  • 1王彧,马士华.供应链环境下集配商供应模式的探讨[J].管理评论,2005,17(2):33-36. 被引量:38
  • 2杨文胜,李莉.基于Stackelberg模型的准时交货激励契约分析[J].系统工程理论与实践,2006,26(3):17-24. 被引量:12
  • 3浦徐进,石琴,凌六一.多供应商准时制惩罚机制与激励机制研究[J].计算机集成制造系统,2006,12(11):1876-1880. 被引量:11
  • 4王玉燕,申亮,李帮义.几种不同的准时交货博弈模型研究[J].管理评论,2007,19(2):57-62. 被引量:6
  • 5BARNES E, DAI J, DENG Shijie, et al. On the strategy of supply hubs for cost reduction and responsiveness[R]. Singapore: National University of Singapore, 2000.
  • 6HAHM J, YANO C A. The economic lot and delivery scheduling problem:the single item case[J]. International Journal of Production Economics, 1992,28 ( 2 ) : 235-252.
  • 7HAHM J, YANO C A. Economic lot and delivery scheduling problem:the common cycle case[J].IIE Transactions, 1995, 27(2):113- 125.
  • 8HAHMJ, YANO CA. Economic lot and delivery scheduling problem:the nested schedule case[J]. IIE Transactions, 1995, 27(2):126 -139.
  • 9KHOUJA M. The economic lot and delivery scheduling proh lem:common cycle, rework, and variable production rate[J].IIE Transactions, 2000,32(8) :715- 725.
  • 10CLAUSEN J, JU S. A hybrid algorithm for solving the economic lot and delivery scheduling problem in the common cycle case[J]. European Journal of Operational Research, 2006,175 (2) ,1141-1150.

共引文献46

同被引文献90

引证文献11

二级引证文献64

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部