摘要
结合河北省三河市垃圾卫生填埋场工程,对垃圾渗沥液处理调节池、污水处理池、提升井结构所涉及的地震作用下的抗震荷载计算、内力计算及长水池无缝、抗裂及防腐蚀设计等问题进行了分析,并提出了相关的设计方法建议和施工中需要注意的问题。
Taking the project of Sanhe Waste Sanitary Landfill Site of Hebei as an example, some problems were analyzed, including calculation of aseismatic load, calculation of internal force, and design of seamless, cracking resistance and anti-corrosion for long pool involved in the structures of regulating tank of waste leachate treatment, sewage treatment pool, and drawing shaft under earthquake actions. The correlative designing suggestions and some problems needing paying attention to in the construction were put forward.
出处
《环境卫生工程》
2012年第2期45-48,共4页
Environmental Sanitation Engineering
关键词
水池结构
抗震设计计算
长水池无缝设计
pool structure
calculation of aseismatic design
seamless design of long pool