摘要
目前,超深基坑没有统一的认定标准,设计及施工存在着许多难点,一旦出现问题会造成较大的经济损失和安全事故。通过一个具体的工程实例,提出了高喷封底和降水井结合的防渗方案。对超深基坑的设计、施工提出了以施工时间最短为管理目标的建议,并总结了经验和教训,以供类似工程参考。
At present, there is no uniform standard for ultra-deep foundation pit, which has many difficult points in design and construction. Once a problem occurs, serious economic loss and safety accident will be caused. Through an engineering example, high-pressure spraying for sealing and dewatering well are put forward for seepage control. It is recommended to take the in the design and construction of ultra-deep foundation pit, provide reference for the similar engineering. shortest construction time as management objective and the experiences and lessons are summarized toprovide reference for the similar engineering.
出处
《路基工程》
2011年第6期147-149,共3页
Subgrade Engineering
关键词
超深基坑
高喷自成防渗体系
封降结合
时间目标
ultra-deep foundation pit
high-pressure spraying self-seepage control system
combination ofsealing and dewatering
time target