摘要
基于模糊数学的基本理论和计算方法,对具有模糊时间参数的施工网络进行了分析,通过比较现有文献,提出了实用的算法。
Nowadays projects suffer from high uncertainty,the traditional methods are out of date day by day.Comparing with the available articles,this paper presents a project netowrk analysis method based on fuzzy sets theory.A network example is worked out to illustrate the use of the proposed method.The method is practical and can be easily computerized.
出处
《湖南大学学报(自然科学版)》
EI
CAS
CSCD
1999年第6期91-96,102,共7页
Journal of Hunan University:Natural Sciences
基金
河南省交通厅资助课题 !"用频谱法对路面质量进行评估"(土三项27# )
关键词
模糊网络
关键线路
公路工程
工期
施工
network analysis
fuzzy sets theory
fuzzy duration parameter
fuzzy network
critical path