基于活动分割的资源优化研究 被引量:2

Research on Resource Optimization Based on Activity Partition
在线阅读 下载PDF
导出
摘要 在假定活动可分割的基础上,针对资源波动问题,提出了一个基于遗传算法的资源优化方法。首先在已知活动工期的基础上,确定项目工期,继而确定关键工序和非关键工序,并利用基于二元表示的遗传算法,对每个可分的非关键活动在其ES(最早开始时间)到LF(最迟结束时间)的范围内进行调整,以优化资源分配。最后引用一个示例,表明了提出的方法在资源优化方面的优越性。 On the assumption of partitioned activities,this paper proposed a new approach for resource optimization based on Genetic Algorithm(GA) to resolve the resource fluctuation problem.The project duration is determined according to the determined activity duration and then the critical procedures and non-critical procedures can be identified.Each partitioned non-critical activity can be adjusted in the range of earliest start time and latest start time by utilizing GA method denoted by binary digit to optimize the resource allocation.A case study shows the superiority of proposed method for resource optimization.
机构地区 中国矿业大学
出处 《工程管理学报》 2011年第2期191-194,共4页 Journal of Engineering Management
关键词 资源优化 活动可分 遗传算法 resource optimization activity partion GA
  • 相关文献

参考文献10

  • 1杨芳,栗峥,袁永博.建筑业可持续发展评价方法研究[J].工程管理学报,2010,24(3):258-261. 被引量:17
  • 2周康,同小军,许进.资源优化模型及遗传算法[J].华中科技大学学报(自然科学版),2005,33(10):59-62. 被引量:7
  • 3Jin-Lee Kim,Ralph D Ellis Jr.Comparing Schedule Generation Schemes in Resource-Constrained Project Scheduling Using Elitist Genetic Algorithm. J.Constr.Eng.Manage . 2010
  • 4Jaeho Son,Kris G Mattila.Binary Resource Leveling Model:Activity Splitting Allowed. J.Constr.Eng.Manage . 2004
  • 5Tarek Hegazy,Wail Menesi.Critical Path Segments Scheduling Technique. J.Constr.Eng.Manage . 2010
  • 6Seyed Hossein Hashemi Doulabi,Abbas Seifi.An efficient hybrid genetic algorithm for resource leveling via activity splitting. J.Constr.Eng.Manage . 2010
  • 7Po-Han Chen,Seyed Mohsen Shahandashti.Hybrid of genetic algorithm and simulated annealing for multiple project scheduling with multiple resource constraints. Automation in Construction . 2009
  • 8A.B.Senouci,N.N.Eldin.Use of Genetic Algorithms in Resource Scheduling of Construction Projects. Journal of Construction Research . 2004
  • 9Sou-Sen Leu,Chung-Huei Yang.GA-based multi-criteria optimal model for construction scheduling. Journal of Construction Engineering and Management . 1999
  • 10Chan W T,Chua D K H,Kannan G.Construction resource scheduling with genetic algorithms. Journal of Construction Research . 1996

二级参考文献11

共引文献22

同被引文献81

引证文献2

二级引证文献19

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部