具有奖惩结构的三级建筑供应链工期协调优化 被引量:3

Time optimization of three-echelon construction supply chain with bonus-penalty structure
在线阅读 下载PDF
导出
摘要 三级建筑供应链包括业主、总包商和分包商、在分析了三级建筑供应链工期优化的一些基本关系式的基础上,考虑资金时间价值和激励机制,建立了具有奖惩结构的三级建筑供应链工期协调优化模型.模型考虑了业主对总包商的总工期激励,以及总包商对分包商的节点工期激励.最后结合一个算例进行了仿真计算和分析,对比了传统工期优化和供应链工期协调优化的结果.结果表明,对于三级建筑供应链的工期优化,具有奖惩结构的供应链工期协调方法可以使项目工期优化的同时,还能使建筑供应链实现帕累托优化;工期激励政策对三级建筑供应链的工期优化效果是显著的. The three-echelon construction supply chain studied consists of the owner,the general contractor and the subcontractor.Firstly,the basic relationships among related parameters were analyzed.On this basis, the project duration coordination optimization model with bonus-penalty structure was proposed,which involves the time value of capital and incentive mechanism.The proposed model considered that how the owner motivates the general contractor in the total duration and how the general contractor motivates the subcontractor in the node duration.Then,a numerical example was simulated and analyzed,and the results of the traditional time/cost optimization and the supply chain coordination optimization were contrasted.The results show that not only the project duration can be reduced,but also the construction supply chain can realize Pareto optimization by using the method of duration coordination with bonus-penalty structure.Furthermore,it is shown that the duration incentive policy has a significant effect on the project duration optimization of three-echelon construction supply chain.
出处 《系统工程学报》 CSCD 北大核心 2011年第1期60-67,共8页 Journal of Systems Engineering
基金 国家自然科学基金资助项目(10801110 70972052) 陕西省重点学科建设专项资金资助项目(107-00X902)
关键词 三级建筑供应链 工期优化 奖惩结构 three-echelon construction supply chain project duration optimization bonus-penalty structure
  • 相关文献

参考文献12

  • 1江嘉旻,孙永广,吴宗鑫.收益激励的优化与最优工期的选择[J].系统工程,2000,18(3):5-10. 被引量:38
  • 2汪应洛,杨耀红.多合同的激励优化与最优工期确定[J].预测,2005,24(2):60-63. 被引量:41
  • 3Dayanand N, Padman R. On modeling progress payments in project networks[J]. Journal of Operation Research Society, 1997, 48(9): 906-918.
  • 4Dayanand N, Padman R. Project contracts and payments schedules: The client's problem[J]. Management Science, 2001, 47(12): 1654-1667.
  • 5何正文,徐渝,朱少英.具有奖励惩罚结构的项目支付进度问题研究:双重角度[J].系统工程理论与实践,2005,25(10):39-45. 被引量:23
  • 6柴国荣,徐渝,雷亮.合同双方联合角度的R&D项目激励机制优化研究[J].科研管理,2006,27(4):110-115. 被引量:8
  • 7Danity A R J, Briscoe G H, Millett S J. Subcontractor perspectives on supply chain alliances[J]. Construction Management and Economics, 2001, 19(8): 841-848.
  • 8Elazouni A M, Metwally F G. Decision support system for subcontracting construction works[J]. Journal of Construction Engineer- ing and Management, 2000, 16(3): 191-200.
  • 9Xue X L, Sun H S and Shen Q P. A Two-level Programming Method for Collaborative Scheduling in Construction Supply Chain Management[M]. Berlin/Heidelberg: Springer, 2007: 290-297.
  • 10Wang C H, Huang Y C. Optimization model for construction project durations using a multistage decision process[J]. Engineering Optimization, 1998, 30(2): 155-173.

二级参考文献54

共引文献93

同被引文献67

引证文献3

二级引证文献22