施工项目工期-成本优化问题的蚁群算法 被引量:24

Using ant colony algorithm to solve construction time-cost trade-off problem
在线阅读 下载PDF
导出
摘要 为了确定施工项目工期-成本均衡曲线,从而为施工项目计划和控制决策提供有效依据,提出了施工项目工期成本优化问题的蚁群算法.该方法利用施工项目工期成本优化问题的组合优化问题本质,将其转化为旅行商问题,利用自适应权重方法将工期、成本两个目标综合成单目标,采用蚁群算法进行Pareto解的搜索.通过两个实例的计算结果表明,该方法可以有效地确定具有实用价值的Pareto解,且具有较高的全局寻优能力和搜索效率,对于具有大规模网络计划的工期成本优化问题的求解是十分适用的. An approach for time-cost trade-off of construction project based on ant colony algorithm was proposed to determine the time-cost equilibrium curve, and to provide more information for decision-making for planning and controlling of construction project. To convert time-cost trade-off problem of construction project into travelling salesman problem because of its characteristic of combinatorial optimization, and integrate the two objectives of time and cost into a single objective in terms of adaptive weight approach, this approach was applied to ant colony algorithm to search for Pareto solutions. The results of two case studies showed that this approach is very effective for determining practical Pareto solutions, and has strong global searching ability and efficiency. So that it is very suitable for solving time-cost trade-off problem of large scale network.
作者 熊鹰 匡亚萍
出处 《浙江大学学报(工学版)》 EI CAS CSCD 北大核心 2007年第1期176-180,共5页 Journal of Zhejiang University:Engineering Science
关键词 工期-成本优化 蚁群算法 组合问题 time-cost trade-off ant colony algorithm combinatorial problem
  • 相关文献

参考文献6

  • 1FENG Chung wei,LIU Liang,BURNS S A, Using genetic algorithms to solve construction time-cost trade-off problems [J]. Journal of Computing in Civil Engineering, 1997, 11(3):184-189.
  • 2KELLY J E. Critical path planning and scheduling:mathematical basis [J]. Operations Research, 1981,9(3): 296-320.
  • 3LIU Liang BURNS S A. FENG Chung-wei. Construction time-cost trade-off analysis using LP/IP hybrid method [J]. Journal of Construction Engineering and Management, 1995, 121(4):446 - 454.
  • 4FONDAHL J W. A non-computer approach to the critical path method for the construction industry [R]. California: Stanford University, Department of Civil Engineering, The Construction Institute, 1961: 131 - 139.
  • 5PRAGER W. A structural method of computing project cost polygons [J].Management Science, 1963, 9 (3):394 - 404.
  • 6DAISY XMZ S, THOMAS N, MOHAN M K. Applying a genetic algorithm-based multiobjective approach for time cost optimization [J]. Journal of Construction Engineering and Management, 2004, 130(2): 168 - 176.

同被引文献153

引证文献24

二级引证文献100

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部