摘要
论述地铁机电设备系统开通试运行前综合联调的作用,认为需要考虑在有限的时间内组织众多的承包商和运营公司各部门来共同完成验证。结合成都地铁1号线综合监控系统大联调的组织和实施情况,对开展大联调的要点进行探讨,同时对大联调的实施提出建议。
Overall adjustment of electro-mechanical equipment system is the last step before putting the system into operation.It is necessary to organize equipment providers and operation departments to complete the work in limited time.Considering the organization and implementation of overall adjustment of ISCS of Chengdu metro Line 1,some key issues are discussed and some recommendations are put forward.