新产品开发项目资源受限—工期优化方法研究 被引量:1

Method Research on Resources Constrained-Duration Optimization in New Product Development Project
在线阅读 下载PDF
导出
摘要 针对资源受限情况下新产品开发项目的进度安排问题,对原资源调配法"RSM"作出了改进,将资源冲突时刻两两比较平行工序的最早开始时间(ES)与最迟完成时间(LF)的差值,转换为寻求平行工序中持续时间最小值D和初始最迟开始时间最大值BLS,从而迅速地确定后移的工序。最后通过算例证明了改进的"RSM"法能显著减少计算量,提高运算效率。 For the problem of scheduling in new product development project under constrained-resources condition,the paper improved the original resource allocation method "RSM" by seeking the minimum value of duration(D)and the maximum value of initial latest start time(BLS)among the parallel processes at the time resource conflict exists,instead of pairwise comparison between their earliest start time(ES)and latest finished time(LF),thus rapidly confirming the processes to be moved back;An example proved that the improved "RSM" notably reduced the computational volume and increased operational efficiency.
出处 《科技进步与对策》 CSSCI 北大核心 2010年第24期100-103,共4页 Science & Technology Progress and Policy
基金 重庆市科委自然科学基金项目(CSTC 2008BB2173)
关键词 新产品开发项目 资源受限 进度安排 改进的“RSM”法 New Product Development Project Constrained-Resources Schedule Improved "RSM" Theory
  • 相关文献

参考文献10

二级参考文献18

共引文献53

同被引文献9

引证文献1

二级引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部