长洲水利枢纽截流试验与现场实施 被引量:2

Experimental Study and Site Implementation of River Closure in Changzhou Hydraulic Complex
在线阅读 下载PDF
导出
摘要 长洲水利枢纽坝址区的两个江心岛泗化洲岛和长洲岛将浔江隔成三江,对任何一江截流,其他两江的流量过程均是非恒定的。这种非恒定流过程对截流时通航水流条件和截流龙口水流条件均产生了进一步的恶化,较大地增加了截流难度。截流试验研究所阐述的现象和问题,在实际截流时得到了较好的再现;所给出的解决方案和工程措施,有效地保证了实际截流工作的顺利完成。 The Xunjiang River is divided into three parts by Sihuazhou Island and Changzhou Island in Changzhou Hydraulic Complex,and the flow will become unsteady when anyone of them is closed.This unsteady flow would make it more difficult to close the river due to further deterioration of flow conditions for navigation caused by river closure.Phenomenon and problems in river closure experiment are all found in the practice,and solutions and engineering measures proposed in this experiment make river enclosure complete successfully.
出处 《红水河》 2010年第5期14-20,共7页 Hongshui River
关键词 截流 通航 模型试验 长洲水利枢纽 river closure navigation model test Changzhou Hydraulic Complex
  • 相关文献

参考文献3

  • 1中水东北勘测设计研究有限责任公司科学研究院.长洲水利枢纽工程技施设计阶段水工整体模型试验报告[R].长春:中水东北勘测设计研究有限责任公司科学研究院,2006.
  • 2中水东北勘测设计研究有限责任公司科学研究院.长洲水利枢纽工程技施设计阶段水工整体模型补充试验报告[R].长春:中水东北勘测设计研究有限责任公司科学研究院,2006.
  • 3南京水利科学研究院.广西长洲水利枢纽鱼道水工水力学试验研究综合报告[R].南宁:南京水利科学研究院,2005.

共引文献1

同被引文献12

  • 1SL303—2004,水利水电工程施工组织设计规范[S].
  • 2董曾南.水利学[M].北京:高等教育出版社,1995.
  • 3武汉水利电力学院水利学教研室.水利计算手册(第二版)[M].北京:中国水利电力出版社.2006.
  • 4冯健.长洲水利枢纽工程二期内江截流设计[J].红水河,2007,26(4):1-4. 被引量:1
  • 5迁江水文站.水文预报[R].来宾:迁江水文站,2007.
  • 6SL163—2010,水利水电工程施工导流和截流模型试验规程[S].
  • 7DL/T5361—2006,水电水利工程施工导截流模型试验规程[S].
  • 8DL/T5260—2011,水电水利工程施工环境保护技术规程[S].
  • 9SL158—2010,水工建筑物水流压力脉动和流激振动模型试验规程[S].
  • 10马雪红,巩平福.长洲水利枢纽工程中江截流设计与施工[J].水利水电施工,2008(2):21-24. 被引量:1

引证文献2

二级引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部