期刊文献+

造船厂钢板出库作业计划的建模及优化研究 被引量:5

Modeling and Optimization on Operation Scheduling for a Steel Plate Yard in a Shipyard
在线阅读 下载PDF
导出
摘要 对于造船厂钢板堆场出库作业计划问题,在分析堆场出库作业流程的基础上,建立了以出库作业时间最短为目标的优化模型。该模型可归结为多层组合优化问题。针对本问题寻优过程的阶段性和复杂性的特点,提出了基于改进遗传算法的多层嵌套启发式优化算法。与传统人工决策的作业方案相比,该优化结果可以缩短24%~67%的作业时间。 To research the operation scheduling for a steel plate yard in a shipyard, an optimization model aiming to minimize the operation time was established based on the analysis of steel plate pick-up operation process. This mathematical model was formulated as a multi-level combinatorial optimization model. Considering the characters of stage and complexity in optimization process,a multi-level nested optimization algorithm based on genetic algorithm was proposed and implemented to solve this problem. The results from this proposed algorithm can shorten operation time by 24% to 67%.
出处 《工业工程与管理》 北大核心 2009年第6期12-17,共6页 Industrial Engineering and Management
基金 教育部留学回国人员科研启动基金资助项目(教外司留[2005]383号文件)
关键词 钢板作业计划 组合优化 遗传算法 多层嵌套算法 steel plate operation scheduling multi-level nested algorithm combinatorial optimization genetic algorithm
  • 相关文献

参考文献12

  • 1Kim H J, Hwang S K, Lee J S. Control of lifting desired number of steel plates and automatic crane operation crane operation[J]. Iron and Steel Institute of Japan International, 2003,43 (2) :230 -237.
  • 2蒋如宏,钟宏才,谭家华.船厂钢板堆场管理的数字化仿真[J].上海交通大学学报,2003,37(8):1242-1245. 被引量:7
  • 3Hansen J,Kristensen T F. Crane scheduling for a plate storage in a shipyard: Modelling the problem[R]. Copenhagen: Informatics and Mathematical Modelling, Technical University of Denmark, 2003.
  • 4Hansen J,Kristensen T F. Crane scheduling for a plate storage in a shipyard: Solving the problem [R]. Copenhagen: Informatics and Mathematical Modelling, Technical University of Denmark, 2003.
  • 5Hansen J,Kristensen T F. Crane scheduling for a plate storage in a shipyard: Experiments and results [R]. Copenhagen: Informatics and Mathematical Modelling,Technical University of Denmark, 2003.
  • 6唐立新,杨自厚.热轧实施计划中最优倒垛问题的整数规划模型及遗传算法[J].自动化学报,2000,26(4):461-469. 被引量:14
  • 7李耀华,王伟,胡国奋,宁树实.热轧板坯库出库计划编制模型与算法研究[J].计算机集成制造系统,2006,12(3):377-381. 被引量:13
  • 8Omar Ben-Ayed,Charles E. Blair. Computational difficulties of bilevel linear programming[J]. Operations Research, 1990, 38 (3):556-560.
  • 9Lan K M,Wen U P,Shih H S, et al. A hybrid neural network approach to bilevel programming problems [J]. Applied Mathematics Letters,2007,20(7):880-884.
  • 10林丹,王宏,李敏强.用多目标进化算法求解二层规划双目标模型[J].系统工程理论与实践,2006,26(5):106-110. 被引量:10

二级参考文献37

  • 1李苏剑,陈宗海.宝钢板坯库出库计划优化模型[J].物流技术,1996,15(1):18-21. 被引量:3
  • 2陈强.[D].哈尔滨:哈尔滨工程大学船舶学院,2001.
  • 3Binkowski M. A queuing model for the design and analysis of a mining stockyard[J]. Theory and Application, 1999, 9(1):75-98.
  • 4Won Y Y, Yong S C. A Simulation model for container-terminal operation analysis using an object-oriented approach[J]. International Journal of Production Economics, 1999, (59) : 221 - 230.
  • 5Lee H S,IBM Journal ofResearch &Development,1996年,40卷,2期,231页
  • 6LOPEZ L, CARTER M W, GENDREAU M. The hot strip mill production scheduling problem:a tabu search approach[J]. European Journal of Operational Research, 1998, 106(2/3): 317-335.
  • 7JAMES K, RUSSELL E. Particle swarm optimization[A].IEEE International Conference on Neural Networks[C]. USA:IEEE Press, 1995, 1942-1948.
  • 8邢文训 谢金星.现代优化计算方法[M].北京:清华大学出版社,2000.141-190.
  • 9Baeck T,Fogel D B,Michalewicz Z (Eds.).Handbook of Evolutionary Computation[M].Oxford:Oxford University Press,1997.
  • 10Deb K,Agrawal B,Pratab A,Meyarivan T.A fast elitist non-dominated sorting genetic algorithm for multi-objective optimization:NSGA-Ⅱ[J].IEEE Transactions on Evolutionary Computation,2002,6(2):182-197.

共引文献41

同被引文献35

  • 1方必和,刘雪梅.一类特殊二维0-1规划的广义指派模型求解[J].运筹与管理,2007,16(3):66-68. 被引量:10
  • 2刘树立,于丽英.人数与任务数不相等的指派问题[J].运筹与管理,2005,14(2):64-66. 被引量:12
  • 3李耀华,王伟,胡国奋,宁树实.热轧板坯库出库计划编制模型与算法研究[J].计算机集成制造系统,2006,12(3):377-381. 被引量:13
  • 4玄光男,程润伟,于韵杰,等.遗传算法与工程优化[M].北京:清华大学出版社,2009:36-38.
  • 5李端,钱富才,李力,高建军.动态规划问题研究[J].系统工程理论与实践,2007,27(8):56-64. 被引量:30
  • 6金淳,廖尧,黄英艺.考虑造船生产顺序的钢板库布局优化模型[J].工业工程管理,2010,15(3):49-54.
  • 7Beasley J E,Chu P C. A genetic algorithm for the set covering problem[J]. European Journal of Operational Research, 1996, 94 . 392-404.
  • 8Chu P C,Beasley J E. A genetic algorithm for the generalised assignment problem[J]. Computers Operations Researeh, 1997,24(1) :17-23.
  • 9PARK C, PARK J C, BYEON G G, et al. Steel stock manage- ment on the stockyard operations in shipbuilding: a case of Hyundai Heavy Industries [ J ]. Production Planning and Con- trol: The Management of Operations, 2006, 17(1): 1-12.
  • 10ZHANG Zhiying, WANG Peng, WANG Weize. Optimiza- tion and operation scheduling for a steel plate yard based on greedy algorithm [ J 1. Journal of Networks, 2013, 8 ( 7 ) : 1654-1659.

引证文献5

二级引证文献7

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部