摘要
华能内蒙古乌拉山发电厂调试过程中,对300 MW直接空冷机组热态冲洗,对其冲洗方法和冲洗原则进行了分析。此方案冲洗过程时间短,效果好。
The paper summed up the experience of hot flushing for 300 MW direct air - cooled unit during commis- sioning for China Huaneng Neimeng Wulashan Electric Power Plant and introduced in details to the flushing method and flushing principle, With which the time expended on flushing is short and of better effect, which may provide a good reference for similar condition.
出处
《黑龙江电力》
CAS
2009年第3期218-221,共4页
Heilongjiang Electric Power
关键词
热态冲洗
直接空冷发电机组
电厂化学
空冷凝汽器
hot flushing
direct air - cooled unit
chemical system in power plant
air - cooled condenser