期刊文献+

大跨度变截面(燕尾段)衬砌台车设计、制造与应用 被引量:9

Design,Manufacture and Application of Lining Bogie used for Large Span & Changeable Section(Swallow-tailed Section)
在线阅读 下载PDF
导出
摘要 在地下工程中,单洞变双洞,双洞变单洞,设计一般采用渐变断面在一定的距离进行过渡,故形象称之为"燕尾段"。变截面过渡段衬砌施工,传统的方法是制作特殊拱架,立模浇注混凝土,施工干扰大,生产效率低,质量难以保证。在宜万铁路沙坪隧道施工中,对大跨度变截面"燕尾段"衬砌台车的设计、制造与应用做了有益的探讨,供类似工程参考。 Designs for transition in underground work will usually adopt the gradual transition within a certain distance from single tunnel to double one or from double tunnel to single one. They are called swallow-tailed section because of the changing shape. The traditional method for lining construction at the transition section is to manufacture a special arch stand, set up mould and then pour concrete, which has a great disturbance on construction, with a low production efficiency and hard to guarantee the quality. During construction of Shaping tunnel on Yiwan Railway, we carried out a deep research on the design, manufacture and application of lining bogie used for large span and gradual transition at swallow-tailed section as reference to similar works.
作者 刘谭升
出处 《铁道建筑技术》 2008年第5期68-71,共4页 Railway Construction Technology
关键词 大跨度变截面 衬砌台车 设计制造 应用 large span changeable section lining bogie design & manufacture application
  • 相关文献

参考文献2

  • 1TB10204-2002(J163-2002)铁路隧道施工规范[S]
  • 2TB10417-2003(J287-2004)铁路隧道工程质量验收标准[S]

共引文献1

同被引文献57

引证文献9

二级引证文献46

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部