摘要
GB/T50326-2006建设工程项目管理规范明确规定对建设项目进行风险管理,而风险管理的第一步就是进行项目风险识别。深入研究了施工项目风险识别的步骤和方法,建议用施工进度风险、质量风险、经济风险、安全风险来进行分类,综合运用专家调查法、流程图法、初始风险清单法进行风险识别。以哈尔滨市磨盘山水库供水工程(二期)施工项目为例,研究施工项目的风险识别和风险报告。
Risk management should applied in construction project, which is regulated in the specification of GB/T50236-2006. The first step of risk management is risk recognization. This paper studies the steps and methods for recognizing risk and suggests to classify the risks to schedule, quality, economy and safety. The Delphi method, workflow method and initial risk list method are used to recognize risk. The project of Harbin Mopanshan Reservoir Water Supply (2^nd term) is taken as an example to analyze the risk recognization and risk report.
出处
《建筑管理现代化》
2007年第5期47-49,共3页
Construction Management Modernization
关键词
哈尔滨市
磨盘山水库供水工程
风险
施工项目风险
风险管理
Harbin
Mopanshan Reservoir Water Supply Project
risk
risk of construction project
risk management