龙滩工程左岸进水口大坝混凝土快速施工工艺 被引量:2

Technology of Fast Concreting at Intake Dam Section on Left Bank of the Longtan Hydroelectric Project
在线阅读 下载PDF
导出
摘要 龙滩水电站左岸进水口大坝集挡水和取水为一体,坝体结构复杂,且4个标段同时施工,相互严重干扰,生产极不均衡,其施工位于控制发电工期的关键线路上。通过合并固结灌浆、采用“先浇板”、增设纵缝和补充混凝土入仓手段等办法,优化了施工工艺,增加了浇筑强度,创造了在狭小空间单日浇筑混凝土5 400 m3、单月浇筑11.7万m3的记录,达到了坝体快速施工的目的。 The dam section at left bank intake of the Longtan hydroelectric project is structurally very complicated as it has two functions, water retaining and water drawing. It suffered severe interference because of eontractors of 4 lots operating simultaneously at the site. It is on the critical path for commissioning of the project. The construe'lion technology was improved through combined consolidation grouting and adoption of the method of "plate concreting first" and increased number of longitudinal joints and means of placement of concrete, The concreting intensity was Jut:teased to a daily placement of 5400 m^3 and a monthly placement of 117,000 m^3, The quick concreting of the dam body was finally achieved.
出处 《水力发电》 北大核心 2006年第4期56-57,共2页 Water Power
关键词 混凝土浇筑 快速施工 施工工艺 龙滩水电站 placement of concrete fast concreting eonstruction technology Longtan Hydropower Station
  • 相关文献

参考文献2

  • 1叶应妩,王毓三主编,中华人民共和国卫生部医政司.全国临床检验操作规程[M]东南大学出版社,1997.
  • 2杜荣骞.生物统计学[M]高等教育出版社,1985.

同被引文献3

引证文献2

二级引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部