多属性虚拟企业部分并行协商项目规划 被引量:18

Partially parallel multi-issue negotiation for project scheduling in virtual enterprise
在线阅读 下载PDF
导出
摘要 在虚拟企业环境下,制定基于盟主与合作伙伴协商的项目规划不仅要考虑任务时间与工期的可行性,而且要关注工期费用。在分析虚拟企业项目协商规划的工期与费用的不确定性的基础上,提出了多属性工期-费用随机项目模型,以及工期-费用部分并行协商规划算法,以期望工期费用为优化目标,结合示例阐述其计算过程。最后针对模具生产的特点,对模具虚拟企业的项目进行仿真规划,仿真结果表明了这一方法的有效性和可靠性。 To formulate a project scheduling between coordinator and negotiating partners in virtual enterprise, not only factors such as project completion time and feasibility, but also project expense, should be considered. Based on analysis of uncertainties in both project completion limit and expense in project negotiation scheduling of virtual enterprise, a multi-issue time-cost stochastic model was put forward. A partially parallel negotiation algorithm for project limit and expense was also advanced, which took project expense within expectation as its optimum goal. The implementation of the algorithm was demonstrated by a simple example. Finally, with consideration of the characteristics of the mould and die manufacturing, simulated scheduling was conducted in mould virtual enterprise. The simulation result indicated that the model was applicable, and the algorithm was reliable and effective as well.
出处 《计算机集成制造系统》 EI CSCD 北大核心 2005年第6期810-817,850,共9页 Computer Integrated Manufacturing Systems
基金 国家863/CIMS主题资助项目(2003AA414023) 国家自然科学基金项目(50085001) 广东省自然科学基金团队资助项目(20003051)。~~
关键词 虚拟企业 项目规划 工期一费用 协商 效用函数 virtual enterprise project scheduling time-cost negotiation utility function
  • 相关文献

参考文献8

  • 1CONRY S E, KAZUHIRO K, LESSER V R, et al. Multistage negotiation for distributed constraint satisfaction [J].IEEE Transactions on System, Man, and Cybernetics, 1991,21(6): 1462-1477.
  • 2BRUCKER P, DREXL A, MOHRING R, et al. Resourceconstrained project scheduling: notation, classification, model, and methods [ J]. European Journal of Operational Research, 1999,112(1) : 3-41.
  • 3FLESZAR K, HINDI K S. Solving the resource-constrained project scheduling problem by a variable neighborhood search[J]. European Journal of Operational Research, 2004, 155(2) :402-413.
  • 4苏志龙,陈庆新,陈新,孙健.CPC环境下的模具虚拟企业项目粗规划[J].机械工程学报,2003,39(1):38-46. 被引量:10
  • 5苏志龙,陈庆新,陈新,孙健.基于协商的模具虚拟企业生产项目规划[J].中国机械工程,2002,13(22):1931-1937. 被引量:11
  • 6LEU Sousen, CHEN Anting, YANG Chunghuei. A GA-based fuzzy optimal model for construction time-cost trade-off[J]. International Journal of Project Management, 2001,19(1) :47-58.
  • 7SHAFTEL T L, WILSON B M. Time-cost evaluation of alternative system/process designs[J]. International Transactions in Operational Research, 1999,6(3) :275-288.
  • 8李建强,范玉顺.虚拟企业环境中的项目调度方法[J].计算机集成制造系统-CIMS,2002,8(3):187-192. 被引量:14

二级参考文献6

共引文献25

同被引文献164

引证文献18

二级引证文献80

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部