摘要
赣州水司在南河水厂2万m^3/d扩建工程的斜管沉淀池设计中,采用竖向配水系统,改善了配水条件并节约了占地面积:采用重力排泥、虹吸放空、排泥管和泥斗压力水反冲一体化的排泥系统,较好地解决了泥斗沉泥易板结和吸泥管易堵塞的问题.
When the expansion work of 20000 cubic meters per day was executed for Nanhe Waterworks in Ganzhou, Jiangxi province in East China, a vertical water distribution system was adopted in the sedimentation tank with laminar module to save the area and improve the operation of distributing process. The applied integral sludge draw-off system including gravitational sludge drawing, syphomatic vacation and pressurized backwashing of sludge draw-off tube and sludge hopper is very helpful to solve the problems such as sludge accumulation on sludge hopper and block up of the sludge tube.
出处
《给水排水》
CSCD
1994年第12期13-13,共1页
Water & Wastewater Engineering