针对机械联合作业过程中,型号不同多台辅助施工机械与主导施工机械配合施工,完成单次土方作业循环时间参差不齐的情况,利用优化方法,建立了不同型号辅助施工机械完成单次土方作业循环时间控制模型.获得了不同型号辅助施工机械与主导施工机械配合施工的最佳序列和循环时间.
When many aid machines and main machines are associated with together to construct, the circling time of finishing one-time earthwork is not equal. According to such situation, the article makes the circling time control model for different types of aid machines to finish one-time earthwork.By using optimization, it gets the optimal queue and circling time for different types of aid machines to associate main machines.