16和18层剪力墙筒体大楼爆破拆除 被引量:8

BLASTING DEMOLITION OF 16- AND 18-STOREYED BUILDINGS WITH SHEAR WALL TUBE STRUCTURE
在线阅读 下载PDF
导出
摘要 介绍了采用控制爆破技术拆除16层和18层剪力墙筒体结构楼房的成功实例。两幢楼房呈纵向直线排列。由于环境限制,只能沿纵向倾倒。为了确保按预定方向倾倒并充分解体,采取了预切割分块和削弱结构强度等措施,并采用了"分片塌落、空中解体、三角立体延时"的爆破方案。此外,简述了保护古城墙的安全措施,并对爆破效果做了简要分析。 This paper introduces the practical example of successfully demolishing 16- and 18-storeyed buildings with shear wall tube structure by controlled blasting. The two buildings are longitudinally arranged in a line. Because of restricted surroundings, longitudinal collapsing is only feasible. In order to ensure directional collapsing and full disintegrating of the two buildings, some technological measures such as pre-cut and weakened structural strength are taken and a blasting scheme of 'piecewise collapsing, air disintegration and diagonal delay sequence' is adopted. In addition, the safety measures for protection of ancient city wall are outlined and the blasting results are briefly analyzed.
出处 《工程爆破》 2004年第2期31-34,16,共5页 Engineering Blasting
关键词 爆破拆除 剪力墙简体结构 控制爆破 空中解体 三角立体延时 Blasting demolition Shear wall tube structure Controlled blasting Air disintegration Diagonal delay sequence
  • 相关文献

参考文献2

二级参考文献2

共引文献13

同被引文献54

引证文献8

二级引证文献43

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部