摘要
本文介绍了古田溪水力发电厂三级电站2号机组尾水管改造工程,改造内容主要包括:(1)尾水管局部更新;(2)尾水进人门更新;(3)尾水管基础灌浆。
This paper introduces the improvement project for draft tube of Unit 2 in the third power station of Gutianxi Hydropower Plant, it includes: the partial reconstruction of draft tube, renewal of draft tube manhole door, the base of draft tube Grouting.
出处
《集成技术》
2013年第1期66-69,共4页
Journal of Integration Technology
关键词
尾水管
改造
draft tube
transform