摘要
介绍了赣龙铁路18标段,复杂地质条件下隧道施工过程中的病害及其整治方法,着重介绍洞内外综合加固技术的方案选择、施工方法、保证措施、监控量测及膨胀围岩段采取的措施。可为同类工程的施工提供一定的借鉴。
This paper introduces the tunnel diseases and curing methods under complex ground conditions in the 18th Contract Section of Gan-Long Railway, with the emphasis laid on the selection of the technical plan for comprehensive strengthening inside and outside the tunnel, the construction methods, ensuring measures, monitoring and survey, and measures adopted in the swelling rock area, which may provide reference for similar works.
出处
《石家庄铁道学院学报》
2004年第B05期1-3,共3页
Journal of Shijiazhuang Railway Institute
关键词
铁路隧道
复杂地质
施工技术
railway tunnel
complex geology
construction technology