深圳地铁一期工程国老区间南段暗挖隧道为单洞双层隧道,地质条件复杂,富含水砂层距离隧道顶部仅0~2m,采取了多种地面和洞内的止水加固措施,积累和形成了该类地层中暗挖隧道止水加固施工技术的经验。
The coveredexcavation tunnel of the south guolao section of the first stage Shenzhen Subway project is a singletunnel and doublefloors tunnel, geological conditions of this area are very complex, and the distance between waterrich sand stratum and the top of the tunnel is about from 0 to 2 meters. Engineers adopted many waterstop and strengthening measures on ground and in the tunnel, and accumulated experience of waterstop and strengthening construction techniques of coveredexcavation tunnels in similar strata.
出处
《施工技术》
CAS
北大核心
2004年第1期43-45,共3页
Construction Technology
关键词
旋喷桩
化学注浆
暗挖隧道
止水加固
地铁工程
covered-excavation tunnel
water-stop and strengthening
spiral spray pile
deep-pore grouting