摘要
在城市轨道交通建设期 ,各参与单位和专业相互间有众多和复杂的接口 ,构成关联紧密的接口体系。接口管理是否能顺利完成 ,对工程的工期和投资有重大影响。每条线的建设单位在工程建设的全过程均应重视接口体系的管理。讨论了各类接口的任务和接口风险及防范措施 。
There are many complex interfaces between engineering departments and professions in UMT construction, which form a closely connected interface system. It is crucial for the time span of a project and the investment whether an interface works well and efficiently. Therefore, the author argues that the management of an interface system during the whole process of a project shall be given great attention for the engineering department. In this article, the author introduces three types of interface systems: management interface, engineering interface and contract interface, each has different functions and risks and needs special guarding measures. Also the information management of the interface system is discussed.
出处
《城市轨道交通研究》
2003年第6期35-40,共6页
Urban Mass Transit