摘要
本文提出了基于累积量法的直接修改模型法安排多区域互联系统发电机组计划检修的新算法,结合由陕、甘、宁、青四省电网组成的西北电力系统编制了发电机组的检修程序,并用该程序对机组的检修进行了优化安排.
This paper presents a new algorithm for scheduling generators to be repaired in a multi-region power system,using dirrectly modifying model method based on the cumu-lant volume method. This method is very fast and good at levelizing the risk , thus having a lower annual risk.It provides a scientific basis for electric power system to operate economically and reliably.A repairing schedule programme has been worked out in connection with the northwestern power system composed of Shannxi,Gansu, Ningxia and Qinghai provinces, and the generator repairing schedule is optimized by using this programme.The result shows that this method is satisfactory.
出处
《陕西水力发电》
1992年第1期39-44,共6页
Journal of Shaanxi Water Power
关键词
发电机组
计划模型
发电
维修
Generating set, Maintenance of equipment, Scheme, model