摘要
主要论述了柳钢棒线厂2号加热炉基础施工中的边坡支护方法,软弱地基处理方案的选择、确定以及通过化学注浆方法提高地基承载力的实践经验。
Discusses mainly the method of side slope support,the selection and determination of poor foundation treatment,and the practice experience of improving subgrade capacity by chemical grouting dur- ing the foundation construction of No.2 heating furnace at Bar and Wire Plant of Liugang.