摘要
在仰山一级站大坝工程施工质量管理和质量监督上采取的措施是:①甲乙双方都建立了质量监督体系,设置了不同层次的质量监督岗位;②坚持甲乙双方联席会议制度;③对单元工程施以质量检测检查,并对单元工程质量进行质量等级评定,在数与质上进行双向控制,经评定:100%单元工程合格,其中优良级的占80%以上;④分阶段对各个工程组织验收。
Measures of quality control adopted at the dam construction of Yangshan First Cascade Hydropower station are as follows: 1.The constructor and the investor had set up its system and positions of quality control. 2.The regularity of their joint conference was kept. 3.The quality checkup and evaluation were adopted to individual projects, so their qualities can be controlled qualitatively and quantitatiuely. It has been found that 100 percent of the individual projects are up to standard and 80 percent of them are excellent. 4.The quality of every project can be checked and accepted by stages.
出处
《江西水利科技》
1992年第3期211-216,共6页
Jiangxi Hydraulic Science & Technology
关键词
监督
坝
施工
质量
管理措施
Quality
Administrate
Control
Measure.