摘要 盾构由于闭胸和建立平衡而易产生的泥饼问题,一直困扰着盾构施工,其不仅影响盾构机选型、施工进度,严重者还影响施工安全。通过解剖典型事例,研究其成因,探讨盾构机选型方面和施工措施方面的对策,其目的是推进盾构工法的进一步优化,为我国正在蓬勃兴起的盾构事业提供借鉴。 Shield machine is inclined to produce mud cake (secondary rock) in operation because of closed chest or balance establishment. It directly influences selection of shield machine, construction schedule, and even construction safety. A typical case is studied to explore the cause of mud cake and the countermeasures of machine selection and construction method to improve construction of shield machine.
机构地区 广州地铁总公司
出处 《地下工程与隧道》 2003年第2期25-29,共5页 Underground Engineering and Tunnels
  • 相关文献

参考文献5

  • 1[英]帕克A 塞尔伍德BW.沉积物的成岩作用[M].中国地质大学出版社,1989..
  • 2Zhu Weibin, Ju Shijian, Xie Baofeng, Luo Weixiong. On the engineering and countermeasures of crossing the Pearl River with two used shield machines in Guangzhou metro Line 2. New Devopment in Rock Mechanics & Rock Engineering. N J, USA: Rinton Press, 2002 : 389 - 394.
  • 3Maidi B., Herrenknecht M., Anheuser L.. Mechanised Shield Tunnelling. Ernst & Sohn, 1995.
  • 4Jancsecz, Krause, Langmaack. Advances of soil conditioning in shield tunnelling. 1999.
  • 5Maidl Dr-Ing Ulrich, Sager Dipl-Ing Hans Joachim. Sticking points. Tunnels & Tunnelling International. 2001,33(1):28-31.