济南军区八一礼堂工程在严密的质量控制下进行快速施工,采取了一系列措施:在管理上分段提出网络计划,化整为零;分段平行流水立体交叉作业;混凝土掺早强剂;33m钢桁架高空组拼;21m钢桁架高空滑行就位;提前插入装修;合理划分工作面等。这些措施的实施使该工程缩短工期达71.6%,且工程质量优良。
A series of measures have been quality-controlled strictly and adopted successively for speedy construction of the 8.1 auditorium project, such as.(1) the critical path method(CPM) in management)(2) the parallel and flow production line as well as the overhead crossing construction,(3) the accelerator admixture of concrete)(4) the hifh altitude of the 33m steel trusses, and the sliding placement of the 2lm steel stresses;(5) the prearranged decoration work as well as the appropriate division of labour and working procedures etc.All these measures have been proved successful, saved time 71.6% and gained a quality construction.