格尔木至拉萨成品油管道有一段长为 2km的桥梁跨越管段 ,为了满足安全运行的要求 ,跨越段管道将从 1号桥改线至 2号桥。介绍了跨越段管道冬季施工方案的制定和实施过程 ,施工经验可供同类管道施工时参考。
A 2km-long crossover products pipeline section in Golmud-Lhasa Productsd Pipeline will be removed from No. 1 Bridge to No. 2 Bridge to meet the needs of local economic development. In the article, the pro-gram of pipeline section removal and new pipe section installation construction in winter and construction process are introduced.
出处
《油气储运》
CAS
北大核心
2003年第3期22-23,共2页
Oil & Gas Storage and Transportation
关键词
成品油管道
跨越段
改线
施工
products pipeline, crossover line, pipeline removal and installation, construction