摘要
介绍了 4 2m高废旧水塔的定向拆除 ,讨论了一种高耸建筑物切口高度的确定方法 ,并在工程中得以应用 ,效果理想。
The directional demolition blasting of a 42m high cbandoned water tower with 42m high is introduced. The method of determining the height of blasting cut of top building is discussed. This method is effectively applied to engineering.
出处
《爆破》
CSCD
2003年第1期62-64,共3页
Blasting
关键词
拆除爆破
定向倒塌
水塔
demolition blasting
directional collapsing
water tower